Nassau Lake Park
Improvement
Association

Neighbors Helping Neighbors,
Many Hands, One Cause...

Nassau Lake Dam Updates

If you have any questions or inquiries regarding the Dam, please direct them to Bob Zimmerman at (518) 766-3377.

The Dam is now complete.   An EAP (Emergency Action Plan) was sent to NYS DEC.

In accordance with the Nassau Lake Dam (NLD) OM&I Program a second Technical Inspection for the new dam was completed on July 12, 2011 by Kyle F Swierski, PE, LLC.  In summary, KFS found the dam to be sound and in good condition, with no observed structural deficiencies.

Technical Inspection No. T2 for Nassau Lake Dam (PDF - 6.70 MB)

See the progress reports below. 

Nassau Lake Dam Project Final Inspection Report  May 2009 (PDF - 1.7 MB)

 

 

 

Welcome

Upcoming Events

Newest Members